Last week, earthwork continued along the south side of IL RT 60 west of Fremont Center Road. The existing guardrail and asphalt shoulder was removed and the subgrade was widened to accommodate a future right turn lane. Pipe underdrain was installed in conjunction with the aggregate base course to ensure proper drainage under the roadway.

Removal of existing storm sewer pipe and structures began along Fremont Center Road. Pavement removal of existing Fremont Center Road was also completed. Work then began to prepare the subgrade of the realigned portion of the roadway as it approaches IL RT 60.

This week, storm sewer work is expected to begin. Earthwork along IL RT 60 east of Fremont Center Road will also be taking place.