Update – 7/30/2021

Last week, work began on the temporary traffic signals at Fremont Center Road and IL RT 60. The signals are expected to be turned on the week of 8/16.

This week, concrete curb and gutter was poured along IL RT 60 and Fremont Center Road. A slipform curb machine was used which allows the curb to be poured without forms and can be completed much faster.

Once curb and gutter work was completed, crews began fine grading the aggregate subgrade under the roadway. Next week, hot-mix asphalt paving is expected to begin.

Please continue to check the project website for updates.