Last week, Fremont Center Road was opened to traffic and the detour was removed. Seed and blanket was completed along Fremont Center Road and along the south side of RT 60. Wetland plugs were planted in the detention basin at the southwest corner of the intersection.

Work also began along the north side of RT 60. The temporary pavement from the previous traffic stage was removed and the contractor began grading the clay subgrade.

This week, the contractor began placing geotechnical fabric, pipe underdrain, and aggregate subgrade along the north side of RT 60. Grading of the ditch alongside the pavement also took place.

Storm sewer work north of RT 60 was also completed this week. The culvert crossing under RT 60 was extended further north to accommodate the widened pavement. Culverts were also installed in the ditch line along the north side of the roadway.

Next week, earthwork on the north side of RT 60 will continue with asphalt paving expected to take place week of 9/6.